The existing outdoor pool facility will be redeveloped and converted into an indoor, year-round aquatic center.
Construction is anticipated to be completed in Spring/Summer 2026.
Progress at a Glance
Planning
Design & Engineering
Bid & Contract Award
Construction
Estimated Project Cost
On June 18, 2024, the City of Irving held a Public Input Meeting to show residents ideas for the new indoor Senter pool, as well as gather their input to develop the facility's design.
Senter Park: Estimated Project Timeline
June 2023
Project Announcement
February 2024
Design & Engineering Phase Begins
Feb. 22, 2024
Design services firm contract awarded by City Council. Feasibility study results presented to City Council.
March 21, 2024
City Council approved the Construction Manager at Risk contract.
June 18, 2024
Public Input Meeting: 6 p.m., Senter Park Recreation Center, 901 S. Senter Road
October 2024
Design & Engineering Phase Ends
November 2024
Project Bid & Contract Award Begins
February 2025
Construction Begins
February 2026
Construction Phase Ends
Spring/Summer 2026
New facility opens to public